  • Jace Christiansen

August 24th Construction Update

The subgrade cut on Cliff Avenue has been completed and the roadway has been shaped and compacted. Geotextile fabric and granular fill has been started on Cliff Avenue starting on the south end and working to the north. In the coming week all the granular fill is scheduled to be installed on the project. Following the granular fill placement, the concrete curb and gutter will be started. Concrete surfacing will follow the installation of curb and gutter. Topsoil continues to be installed along the areas of the project where the concrete work has already been completed.


Granular Fill Placement on South Cliff Avenue