August 9th Construction Update
Despite the rain event over the weekend good progress has been made on the underground utilities. The storm sewer pipe for Phase 2 is nearing the final stages. The storm sewer boxes have started and will be ongoing throughout the coming week. Grading of the roadway will likely start in the coming week followed by granular fill.
The detour route through Tom Sawyer Trail and Kent Street will be moving to 272nd Street in the coming week. The detour route signage will be changing, and an updated map will be found under the Information tab of this website.