July 6th Construction Update

Work continues to progress after the holiday weekend. Concrete work on Willow Street east of Cliff Avenue (Phase 1) is well underway and is expected to be completed this week. The fine grading of the granular fill will follow the concrete work in preparation for asphalt pavement. There will also be grading work occurring on Willow Street west of the concrete pavement in preparation for asphalt pavement. The box culvert under Willow Street has now been installed.

The Cliff Avenue closure is still scheduled for the week of July 17th. There will be message boards installed prior to the closure with more information.


Crew Pouring Concrete on Willow Street

201 views0 comments